City HallTuesday, November 10
The developer says a Sioux Falls data center could bring in $10.6 million a year for the state
The Good Day Sioux Falls team
If you've wondered what the developer would say to the city, Gemini Capital founder Michael Anvar took questions Monday night at the Regulatory Oversight Committee meeting at Carnegie Hall. Dakota News Now reports the land is at the southeast corner of East Rice and Veterans Parkway. Anvar said Gemini's models show roughly $5 million a year in municipal electricity taxes and another $10.6 million a year to the state, depending on what's actually built.
Gemini's models show more annual revenue for the state than the city
Sources: Argus Leader, dakotanewsnow.com
View as table
| Value | |
|---|---|
| City electricity taxes | $5 million |
| State revenue | $10.6 million |
Anvar said Gemini worked with Xcel Energy so costs aren't shifted onto residents, and that a closed-loop cooling system would use substantially less water. He couldn't quell concerns about noise.
- End user: none yet; final design waits for one
- Track record: Gemini hasn't developed a data center yet
- Earliest energized: late 2028 or 2029, after an end user
Want your say? Materials for the next meeting are due Nov. 27, and we suggest sending yours in early.
The committee's next steps run from Nov. 12 to Nov. 30
- Nov. 12Committee members tour centers in Nebraska.
- Nov. 27Last day for community members to submit materials for the next meeting.
- Nov. 30The committee's next meeting is scheduled at Carnegie Hall.
Source: dakotanewsnow.com
Sources: Argus Leader, Dakota News Now